Purpose of Note
This guidance note has been written to highlight the rationale for, and explain the implementation of independent reviews of large, complex, innovative or unusual structures. It also applies to more common structures but where there may be abnormal risk e.g. complex ground conditions, adjacency of existing structures.
The purpose of the independent review is to add value to a project by questioning the design team on their hazard elimination and risk reduction measures relating to the design, construction, use, maintenance and decommissioning of the structure. The concept of an independent assessment is not new; it is a well established process. The Highways Agency has adopted a system of independent checks on most highway structures for many years; the nuclear, and other specialist sectors also adopt rigorous review procedures. Some enlightened private sector clients have also seen the benefits. Although the detail and approach of these client-instigated reviews may vary they all have the common aim of reducing risk and adding value to the project.
However, although the process set out in this note operates through an independent reviewer in common with the examples quoted above, it differs in its approach from most existing examples. The key characteristics of this process are that:
- It is a high level 'review', not a 'check' as conventionally performed (that is for others).
- The reviewer is seen as the designers 'critical friend', whilst retaining independence
- The design team retain ownership of the design but are challenged to justify and consider design decisions and their impacts.
- The reviewer is able to act objectively without attracting liability.
- It should be an iterative process i.e. the reviewer becomes involved at an early stage and contributes throughout the design development.
Independent Review of Building Structures
1 For some time SCOSS has been considering how best to promote the public safety requirements inherent in large or complex projects, where currently there is no accepted adoption of independent review. The concept of independent reviews is considered useful since these already exist across our industry albeit in an inconsistent way. Most highway structures undergo some form of independent check1; in potentially hazardous industries there is a process of independent design verification (e.g. in the nuclear industry and in the entertainment rides industry, both of which involve public safety governed by the integration of several engineering disciplines such as civil, structural, mechanical and control). Although building structures are submitted to Building Regulation control that process is often too mechanistic to tease out safety issues inherent in major structural or infrastructure projects, which often fall outside the scope of routine regulation and, on occasions, outside the scope of standard Codes of Practice (and sometimes the experience of building control reviewers). Building Regulations only deal with the finished state and not with the construction stage (when the risk of failure is often higher) or with structural maintenance considerations.
2 The independent review is not a further layer of bureaucracy; it is designed to be useful to all parties and to assist in reducing risks and adding value to the project. As noted above, it is already accepted in specific sectors as a client-sponsored safeguard which recognises that the wider benefits outweigh the additional cost.
Objective of independent review
3 The usual objectives are to review:
- Design philosophy (including the design safety objectives)
- Major hazards and ascertain if they have been identified and dealt with2.
- The robustness of the structure and whether it has been adequately considered.
- Models of analysis and that they have been adequately validated by the designers. Also, to ascertain that the results have been reviewed in terms of magnitude and pattern.
- Design assumptions including the relationship to construction, use and maintenance, materials and specification.
- Design interfaces.
- Procurement and contractual arrangements including their compatibility with structural robustness.
4 However it is worth noting that there is often benefit to the project if the scope of such a review is widened to include other project issues: for example client brief, expected deliverables and finance; sustainability issues could also be included. This is the holistic approach.
Selection of structures
5 The selection of structures (including temporary works structures) for independent review should ideally be based on risk. Given the practical difficulties of doing this however, and the likely need for guidance, it is proposed that the structures are generally chosen according to the categories of structure used in Table 11 of the Building Regulations, Approved Document A. These were derived from a risk related analysis.
6 Hence, it is recommended that any structure which falls into one of more of the following categories should be subjected to an independent review:
Category |
Example |
| Potential hazard to large numbers of people |
Theatres, stadia, large offices, underground stations, tunnels, bridges, long or deep retaining walls, |
| Are of critical design, materials or form |
Use of specialist software in safety critical situations,
Minimal redundancy,
Tall structures,
Use of new proprietary products where these perform key structural functions,
Buildings designed using tests or first principles, rather than code formulae,
Buildings with elements outside primary code limits
Structures with complex and critical soil/structure interaction.
Structures requiring special construction techniques |
| Have to resist significant and unusual hazards |
Industrial processes, significant impact forces, terrorist actions, significant climatic effects. |
| Where procurement and contractual arrangements are critical |
Use of design/build in complex situations; use of self-certification; |
| Have a crucial design/construction interaction |
Structures with critical temporary stability or temporary works requirements. |
|
This approach aims to select projects which are large, complex, innovative or unusual (a suggestion already promoted by others) and those with high risk.
7 This categorisation derives from a structural safety perspective. However, there may be compelling grounds for an independent review on economic, insurance, business criticality or similar grounds. (The chosen categories tie in with, and expand on, the suggestions made in the SCOSS 14th Biennial Report).
Implementation of review
8 The review may be carried out by someone (or a team) from the same organisation as that originating the design, or by an external reviewer. However they must be independent of the originating team.
9 Suggested 'rules' for conducting the review are proposed as follows:
i) To be of value, the review must be conducted at high level*. It will be to consider whether the design principles are sound, that the construction proposals are properly considered and adequate proposals are in place for execution. To complete such work satisfactorily, the reviewer(s) must be thoroughly experienced and technically aware across the full range of disciplines, design and construction phases, inherent in the project. The reviewer(s) must be technically skilled to a level whereby design submissions can be properly appraised.
*The parallel activity of design calculation and code compliance checking should continue to take place.
ii) To be of value, all parties in the project must regard the reviewer as a 'critical friend to the team'. In turn, that implies willingness by the reviewer to help resolve problems in an open manner without loosing independence. The reviewer must therefore be someone of integrity, not to be swayed by contractual positions but equally ethically bound not to use confidences to the contractual detriment of any party. The reviewer's duty is to act independently of the team, but to the benefit of all.
iii) If the reviewer is to provide maximum assistance, in order to help resolve the inevitable difficulties that arise, (s)he must not be constrained in offering best judgement for fear of financial penalty (civil action), notwithstanding the obligation to use reasonable skill, care and diligence.
iv) The reviewer must be independent of the team. However, the interaction with the team should be flexible and open with the emphasis on reducing risk and adding value. The review should commence at an early stage so that key project decisions may be considered in a contemporaneous manner. A key focus should be placed on safety and risk reduction through highlighting and addressing concerns. This can very effectively be achieved through presentations by the team to the reviewer along with the generation and maintenance of risk registers. The reviewer should point out errors or concerns and allow the designers to explain their rationale; solutions must be fully owned by the team.
v) The team should be encouraged to provide the written draft reports and outputs, stemming from presentations, workshops and discussions with the reviewer. The drafts are then assessed and commented on as appropriate by the reviewer. This process thus serves as a useful check on communication and also enables the input and value from the reviewer to be maximised. It also places the onus on the team to address the issues and develop solutions thus maintaining the necessary ownership. However, whilst the onus is on the team, it does not preclude the reviewer from pro-actively making constructive contributions.
vi) The cost of the review must be proportionate to the risk i.e. it must add value; it is a matter of negotiation between the parties. However the budget must be reflect the required input if the process is to bring any real benefit to those more directly involved.
Liability of the Reviewer
10 In order for the independent review concept to work efficiently and to bring added value to the project it is essential that those undertaking the role, whilst using due skill care and diligence, are not constrained by fear of formal action (para 9 iii).
11 If the reviewer comes from the same organisation that is employed to design the facility, then the question of liability (in the corporate sense) does not arise. It is then a question of ensuring that internal procedures and culture allow and encourage the reviewer (as an individual or group) to act according to their professional judgement.
12 If the reviewer is from a separate organisation from that of the designers then, appointment documents should be constructed to avoid subsequent action. This might appear to be radical; however, if the process is conducted as suggested, with the reviewer being the 'team's friend' and of established reputation, and ownership of change rests with the designers, it becomes a logical approach.
Footnotes
1 This includes a code compliance check; some view the check as risk averse, which is different from the approach suggested in this note.
2 see for instance the reference to 'abnormal hazards reasonably foreseeable' in Approved Document A para 5.1e. Examples of such hazards are also given in a topic paper on the publications page of the SCOSS website (Topic paper - A risk managed framework for ensuring robustness).
|